August 28, 2026 update
On August 25, Mayor Mark Sager sent a letter to the Inspector of Municipalities detailing the resolution Council passed at its July 20, 2026, regular meeting requesting a provincial review of the North Shore Wastewater Treatment Plant project under Section 765 of the Local Government Act.
August 10, 2026 update
At its regular meeting on July 20, Council approved a motion requesting a provincial review of the North Shore Wastewater Treatment Plant project under Section 765 of the Local Government Act.
The following motion was added as new business to the Council agenda and, following discussion, was approved unanimously.
WHEREAS the North Shore Wastewater Treatment Plant (NSWWTP) project was originally budgeted at approximately $700 million and scheduled for completion in 2020, and is now projected to be completed in 2030 at an estimated cost of approximately $3.86 billion;
AND WHEREAS North Shore residents are expected to bear a disproportionately higher share of the project's costs than residents in many other Metro Vancouver municipalities;
AND WHEREAS Metro Vancouver has initiated an independent review of the project, while a review under Section 765 of the Local Government Act would provide an independent statutory process with powers unavailable to a non-statutory review;
AND WHEREAS Section 765 of the Local Government Act authorizes the Inspector of Municipalities to review matters relating to a regional district;
AND WHEREAS a review under Section 765 would provide an independent and transparent examination of the project, help strengthen public confidence, and enhance accountability in the governance and delivery of major regional infrastructure projects;
AND WHEREAS any provincial review should be undertaken in a timely manner while avoiding unnecessary delay to the project;
THEREFORE BE IT RESOLVED THAT the Council of the Corporation of the District of West Vancouver endorse the unanimous July 6 requests of the City of North Vancouver and the District of North Vancouver and the July 13 unanimous vote from the City of New Westminster to formally request that the Inspector of Municipalities exercise the authority provided under Section 765 of the Local Government Act to commence a review the North Shore Wastewater Treatment Plant project;
AND BE IT FURTHER RESOLVED THAT the Inspector of Municipalities be requested to examine the factors contributing to the project's significant cost increases and delays, and provide recommendations to strengthen governance, transparency, accountability, financial oversight, and public confidence in the delivery of major regional infrastructure projects;
AND BE IT FURTHER RESOLVED THAT copies of this resolution be forwarded to the Inspector of Municipalities, the Minister of Housing and Municipal Affairs, Metro Vancouver, the City of North Vancouver, the District of North Vancouver, and all Metro Vancouver member municipalities.
September 2024 update
The North Shore Wastewater Treatment Plant (NSWWTP) is a new facility currently under construction that will serve over 300,000 residents and businesses in the District of West Vancouver, District of North Vancouver, City of North Vancouver, and Sḵwx̱wú7mesh Úxwumixw (Squamish Nation), and səlilwətaɬ (Tsleil-Waututh Nation). The new plant is designed to support anticipated population growth and treat wastewater more effectively and sustainably which will improve the quality of treated wastewater released into the Burrard Inlet.
The NSWWTP will replace the existing Lions Gate Wastewater Treatment Plant which is at the end of its operational life and must be replaced to comply with new federal regulations that require a higher level of treatment. First announced by Metro Vancouver in 2011, the NSWWTP project originally had an estimated regional cost of $700 million, which was later raised to $1.058 billion. However, since then, several factors have led to a revised cost of $3.86 billion.
Metro Vancouver funds capital expenditures mainly by debt financing and contribution to capital (based on a pay-as-you-go philosophy). The typical debt amortization term for Metro Vancouver utility projects is 15 years, however, to minimize impacts to North Shore ratepayers, the NSWWTP project will be amortized over 30 years. In addition, Metro Vancouver approved a separate cost allocation and phasing to the four sewerage areas for this project. For the North Shore Sewerage Area, the incremental costs would be phased in over five years and costs for the other sewerage areas will be phased in over one year.
While Metro Vancouver sets the overall funding framework, each municipality decides how to recover its portion of these costs. The District of West Vancouver is proposing to recover the incremental costs through a special North Shore Wastewater Treatment Plant Levy, using an approach tied to property assessments.
The FAQ below provides detailed answers to some of the most common questions about the project, funding, and the impact on District residents and business owners.